Time and Cost Performance Analysis of Local And International Contractors on Structural Work of High Rise Building Projects in Addis Ababa

No Thumbnail Available

Date

2021-10

Journal Title

Journal ISSN

Volume Title

Publisher

Addis Ababa University

Abstract

rise building (HRB) projects at industry level and based on the study it recommends solution to full fill the gap between them and indicate that such projects should be implemented by local contractors (at least 85%) as its implementation is much connected to country’s development. The other objective of the research is to explore whether all political, economic, social, technological, environmental and legal factors (PESTEL) have very close relationship with high rise building construction and to aware all stake holders in development of country’s PESTEL. However unless such projects are not implemented by citizens of the country the development of the country and the welfare of the citizens will not be achieved because the jobs were occupied by foreigners and need of too many foreign currencies for international contractors. Different literatures are reviewed to show the relationship between the implementation of high rise building and country’s PESTEL development. This research was attempted to assess the current situation and formulate and give recommendations with respect to high rise construction in accordance with the outcome of the paper. The main tools for the collection of data included case study, questionnaires, interviews and site visit were used to identify the various efforts that have been made in the past and to evaluate and examine the reason of hiring foreign contractors on HRB construction project. Simple statistical analysis involving tables and percentages were used in analyzing the results from the questionnaire. The analysis and discussion part classifies causes of performance difference in to four major parts, that is the General, Managerial, Technological and Technical parts. Hence according to the case study, the respondents and analysis of data the single out standing cause of hiring international contractor is lack of foreign currencies which is found in Managerial part. Again based on top fifteen factors analysis the Managerial part contributes more factors which causes hiring of international contractors such as, poor enterprise management and poor quality management. As per the result of this study the researcher recommends that there should be a mechanism that local contractors get foreign currency in timely manner with the help of government and all stakeholders. In addition to that managerial capacity of local contractors should be continuously upgraded by on job and off job training with cooperation of government and concerned stakeholders.

Description

Keywords

High Rise Building, Foreign Currency, Industry, International Contractors, PESTEL, Quality, Performance difference, Stakeholders

Citation