Abstract
Out of the total population of Ethiopia about 85% live in rural areas and the accessibility of
electric is estimated to be less than 1%. Lack of electricity in rural area has its own negative
effect in human health and economic development. Since the area is dispersely populated and
lacks of infrastructure, it is not easy to generate and distribute electrical energy from the main
rivers to the people living in rural areas. To solve this problem, the main suggestive solution is
implementing stand alone and hybrid power system. Micro hydro power together with solar PV,
wind and biomass will enable electricity accessible to the rural areas.
In this thesis, the feasibility of microhydro/
wind/solar PV and biomass hybrid power system is
studied in the selected rural areas of Ethiopia. The selected villages are located in North west part
of the country known as “Kidusyohanes”,”Kundab” and” Debre”. The feasibility has been
studied by collecting the necessary data and analyzing with the help of HOMER(Hybrid
Optimization modeling for Electric Renewable) software. Data for microhydro
power is
collected from the field sought and Ethiopian Ministry of Water & Energy (MoWE). Solar and
wind data are collected from National Meteorological Agency of Ethiopia and other data sources
such as NASA and SWERA. For the biomass, the data is collected from Local Agricultural and
Rural development office to use the dung for the source of bio energy. The electric load for the
community is estimated and scheduled based on the socio economic activity of the people in the
area. The peak primary load is found to be 212,237,155kw for kidusyohanes, Kundab and Debre
respectively. The peak deferrable (water wheel pump and Irrigation pump) load is 4kw for
kidusyohanes and Kundab, and 3.3kw for Debre. For the next 10 years, the load demand will
increase to 279.8(23.74%), 307.2(21.8%) and 195.0(17.36%)kw for Kidusyohanes, Kundab and
Debre respectively.
From the study the combination of Hydro/PV, Hydro/Biomass and PV is found with the least cost
energy of $0.246/kwh, $0.218/kwh, $0.285/kwh for kidusyohanes, Kundab & Debre respectively.
For Kidusyohaness 34%, Kundab 49.6% and Debre 34.9% excess energy is found from the
simulation result. For Debre the simulation result shows that the system is supported with 294KW
PV/685 S4KS25P when the diesel is included and 285 kw PV/700 S4KS25P when the diesel is
excluded. The COE is $0.285 and $0.279$/kwh for system with & without diesel respectively.
Key words:Feasibility,
microhydro
power, wind, solar, biomass, hybrid, load estimation and scheduling.