Study of Blackouts on Ethiopian Electric Power Network and Identification of System Vulnerabilities

No Thumbnail Available

Date

2017-10

Journal Title

Journal ISSN

Volume Title

Publisher

AAU

Abstract

The Ethiopian Electric Power (EEP) has been operating and managing the national interconnected power system with dispersed and geographically isolated generators, complex transmission system and loads. In recent years, with an increasing load demand for rural electrification and industrialization, the Ethiopian power system has faced more frequent, widely spread and long lasting blackouts. To slash the occurrence of such incidents, analysing the reasons and the mechanisms of these blackouts is the first step in this direction. In this study the causes, mechanism and extent of the past blackouts in the EEP grid are investigated. This is accomplished by collecting the blackouts data from the National Load Dispatch Centre (NLDC) archive. These data are characterized based on four significant indices, namely- number of customers without service, loss of load (MW), duration of blackouts, and their severity level. The investigation is made by considering the following sequential phases of the blackout: system condition prior to the power failure, initiating events, cascading events and the final state of the power system. Based on analysis of the available data, it is found that the major initiating events for the blackouts of the Ethiopian power grid are short circuits, overloads, loss of generations, protection and communication system failures, switching and temporary transients. It is further observed that 49 blackouts were happened on the national grid from 28 th January 2013 to mid of May 2016. It is also found that the highest load loss of 1401.04 MW, which occurred on 28 th November 2015. The 27 th July 2015 blackout duration was the longest and it lasted for about 22 hours. Furthermore, it is observed that 81.25 % of the blackouts (26/32) are having a severity level of 10 to 100 system-minute. These are classified as “Severe” and the remaining 18.75 % of the blackouts (6/32) are having a severity level of greater than 100 system-minute and are classified as “Very Severe”. Simulations studies are carried out using DIgSILENT PowerFactory software to further investigate the initiating events resulting in cascaded tripping and subsequent blackouts. In the first stage, power flow simulation studies are carried out to analyse the system performance under steady state conditions and to determine the voltage magnitude at critical buses and the loadings of lines, transformers and generators prior to the disturbance. In the second stage, time domain Root Mean Square (RMS) simulations are performed to analyse the system performance under transient conditions for the specified initiating and cascading events. A vulnerability analysis was performed using indices called active power performance index (PI p ) and voltage performance index (PI v ). These indices provide a direct means of comparing the relative severity of the different line outages on the system voltage profiles and loadings. It is found that the line outage of Debre Markos_Sululta 400kV line is the most severe line outage having a line loading performance index of 7.3238 pu. The outage of this line resulted in the overloading of eight components. On the other hand, the outage of Alamata_Combolcha 230kV line is found to be the most severe line with respect to the voltage performance index (PI v ) of 0.1124 pu. Based on this analysis, it is found that the most vulnerable buses of the network in respect of voltage limit violations are Sululta and Gefersa 132kV buses. It is further observed that 11 different line outages led Sululta and Gefersa 132kV buses to have voltage magnitudes of below 0.90 pu. The highest percentage voltage deviations for these buses are -14 % and -13 %, respectively. Furthermore, it is found that the network element’s most vulnerable to overload is the transformer at Combolcha II 230/132kV substation, in which 12 different line outages led this transformer to become overloaded. Finally, from the simulation results and system vulnerability analysis, we identify the remedial steps to coordinate and focus control actions that could mitigate the consequences of the disturbances and reduce the risk of cascading events leading to system blackouts. It is recommended that proper protection system coordination, high-speed fault clearing, proper planned interruptions as well as adhering to the security rules and criterions during planning and operation of the power system are the remedial measures that could be explored by EEP

Description

Keywords

Power system blackouts, Blackout indices, Cascading failures, Transient stability, System vulnerability, Contingency analysis

Citation