Preparation and Implementation of Construction Works Program in Era Road Projects
No Thumbnail Available
Date
2014-11
Authors
Journal Title
Journal ISSN
Volume Title
Publisher
Addis Ababa University
Abstract
One of the most important responsibilities of construction project management is the planning and
scheduling of construction projects. The problem of using improper construction works program in
ERA road projects is one of the causes for delay of projects and these have a debilitating effect on
parties to a contract in terms of a growth in adversarial relationships, distrust, litigation, arbitration,
cash-flow problems, and a general feeling of apprehension towards each other.
This study focused on the preparation and implementation of construction works program in ERA road
projects. The objectives of the study were achieved through a desk study, interview and questionnaire
survey to identify the ways of preparation and implementation of construction works program,
challenges and to seek the improvement methods.
A ranking system using the Relative Index (RI) method had been adopted to find the most significant
factor for each section in questionnaire.
Most important tasks identified for the preparation of construction works program were to define the
scope of work to be performed using work breakdown structure, estimate durations for each defined
task using tender quantities, expected crew-size and historical outputs for similar work, defining
working calendars, develop activity dependency.
During implementation the most important were work program should be updated to recognize delay,
using construction time effectively and applying proper efficiency is critical and proper resource
utilization is used to avoid cost overrun.
According to the findings from the questionnaire responses, desk study and interview the major
challenges in preparation and implementation of construction works program were cash flow problem
of contractors, delay in site mobilization by contractor, the climatic condition at site, design change and
right of way problem.
The results of this study indicated that the most recommended improvement methods were contractor
should manage his financial resources and plan cash flow, there should be a continuous, proper
planning before construction, so that resources and time are sufficient and there should be a good
attitude among professionals regarding construction works program.
This study is therefore, to suggest improvement methods which can help to use construction works
program properly in road projects.
Key words: Preparation and implementation, challenges, improvement, ERA road projects.